News & Insights
Legal Alert

The budget reconciliation bill signed into law on July 4 (also known as the “One Big Beautiful Bill”) adds a new provision to the National Environmental Policy Act (NEPA) that allows project sponsors/applicants to pay for expedited completion of an environmental review document. This is the latest in a recent spate of congressional and executive branch actions intended to speed up the environmental review process under NEPA, which requires federal agencies to analyze environmental impacts of projects that they carry out (including private projects that require federal agency approval or receive federal funding).
Under existing law (NEPA Section 107(g)(1), which was enacted in 2023), a lead agency must complete an environmental assessment (EA) within one year and an environmental impact statement (EIS) within two years. These deadlines begin to run from the earliest of the dates that the lead agency, as applicable, (1) determines that NEPA requires the preparation of an EA or EIS, (2) notifies the project applicant that its application to establish a right-of-way for the project is complete, or (3) issues a notice of intent (NOI) to prepare an EA or EIS. Section 107(g)(2) provides that if the lead agency is not able to meet this deadline, it may extend the deadline, in consultation with the project applicant, to provide only so much additional time as is necessary to complete the EA or EIS. Under Section 107(g)(3), if the lead agency does not meet required deadlines, a project applicant can seek a court order compelling the lead agency to act.
The budget reconciliation bill adds a new Section 112 to NEPA, which allows project sponsors to pay an optional fee to cut in half the deadlines for completing an EA or EIS. An earlier version of the bill had also exempted these expedited EAs or EISs from any judicial review, but that aspect was removed from the bill after the Senate Parliamentarian ruled that it was ineligible under the Senate’s budget reconciliation rules. Here is how the new provision in Section 112 works:
Notably, Section 112 puts the start of the environmental review timeline for an EA in the project sponsor’s control (i.e., when it pays the required fee). This is different from the timelines for completing non-expedited EAs as well as both expedited and non-expedited EISs: In those circumstances, the timeline starts upon action by the lead agency; conceivably, a lead agency could delay the start of the environmental review timeline by, for example, requesting additional studies and project information from the applicant before deeming a right-of-way application complete or issuing a NOI.
While this new provision appears to be straightforward — pay a fee in exchange for expedited completion of an EA or EIS — a number of questions remain about how it will be implemented by federal agencies, including:
Allen Matkins will continue to monitor developments in this space, including any implementation guidance that CEQ or other agencies may issue.
Authors
Partner
Senior Counsel
RELATED SERVICES
News & Insights
Allen Matkins Leck Gamble Mallory & Natsis LLP. All Rights Reserved.
This publication is made available by Allen Matkins Leck Gamble Mallory & Natsis LLP for educational purposes only to convey general information and a general understanding of the law, not to provide specific legal advice. By using this website you acknowledge there is no attorney client relationship between you and Allen Matkins Leck Gamble Mallory & Natsis LLP. This publication should not be used as a substitute for competent legal advice from a licensed professional attorney applied to your circumstances. Attorney advertising. Prior results do not guarantee a similar outcome. Full Disclaimer